What the CEA safety regulations 2023 ask of a factory with its own HT installation
Updated 30 October 2026. Next review 30 November 2026.
A factory with its own HT installation owes four things under the CEA safety regulations 2023: an Electrical Safety Officer once connected load passes 250 kW, approval (or self-certification, below the state's notified voltage) before any new or altered installation is energised, periodic inspection at the interval its state sets (never beyond five years), and records an Electrical Inspector can ask for.
The Central Electricity Authority (Measures relating to Safety and Electric Supply) Regulations, 2023, usually shortened to the CEA regulations 2023, were notified on 8 June 2023 and replaced the 2010 set. If you still search for "rule 30" or "rule 43", the 2023 numbers are regulation 32 and regulation 45.
Does the factory need an Electrical Safety Officer?
Yes, if the factory is registered under the Factories Act, 1948 and its connected load is above 250 kW. Regulation 5(3) puts the duty on the owner or management to designate an Electrical Safety Officer (ESO). Mines and oil-fields have a higher trigger of 2,000 kW, which is where the 2,000 kW figure in older summaries comes from.
The ESO needs a degree in electrical engineering with five years of operation and maintenance experience, or a diploma with ten (regulation 5(2)).
The ESO carries out the periodic tests the relevant standards recommend and inspects the installation at intervals not exceeding one year. Results go into the Schedule II form that fits the installation, together with the test reports, a register of safety recommendations the owner has acknowledged, and a record of what was done about each one. The Electrical Inspector can ask to see all of it. For an HT factory the form is Form III.
Who inspects an HT installation, and how often?
The state's Electrical Inspector inspects installations above the state's notified voltage, and owners self-certify at or below it. The interval is not fixed centrally. Regulation 32(2) leaves the period to the state government and caps it at five years, so the figure that governs your plant is whatever your state's inspectorate currently directs.
That gives a factory two calendars: the ESO's yearly check inside the plant, and the state's statutory inspection on its own cycle. The spread between states is real. Goa's periodic-inspection checklist for its Electrical Inspector asks for an application covering HT installations once every 2 years and LT installations once every 4 to 5 years (the document is undated). Do not read that as a rule for your state.
Who signs what
Five different people can sign something in this regime, and each signs something different. The Electrical Inspector approves, the owner self-certifies, a Chartered Electrical Safety Engineer assists with that self-certification, the Electrical Safety Officer tests and keeps the records, and a licensed contractor does the work. Whoever signs, regulation 32(8) leaves the owner responsible for keeping the installation free from danger.
Who | What they do | Regulation |
Electrical Inspector | Inspects and approves installations above the notified voltage, before supply starts and at periodic inspection | 32(1), 45(3) |
Owner | Inspects, tests and self-certifies installations at or below the notified voltage, and files the report in the Schedule II form. The report counts once the Inspector's office receives it, and is deemed received if not acknowledged within three working days. The owner may ask the Inspector to inspect instead | 32(3), 45(1) |
Chartered Electrical Safety Engineer | Authorised by the state to assist the owner with self-certification. Names go on the state's web portal | 6 |
Electrical Safety Officer | Yearly tests and inspection inside a factory above 250 kW, and the records | 5(3) |
Licensed electrical contractor | Does the installation work under a certificate-of-competency holder. Work done any other way cannot be energised or connected | 31 |
A Chartered Electrical Safety Engineer helps with self-certification, so that signature matters only for installations at or below your state's notified voltage. For most HT installations the signature that counts is the Electrical Inspector's.
Where the notified voltage line sits
"Notified voltage" is the line each state draws between self-certification and inspection by the Electrical Inspector, and the regulations leave the number to the government. The Centre has notified 11 kV, Maharashtra set 11 kV in 2019, and Delhi notified up to 33 kV in 2017. A 33 kV factory substation therefore falls on different sides of the line depending on where it stands.
Jurisdiction | Notified voltage | Source |
Central Government | 11 kV | Ministry of Power written reply in the Rajya Sabha, 5 August 2024 (PIB release ID 2041636) |
Maharashtra | 11 kV | Government of Maharashtra order of 19 July 2019, cited in an MSEDCL circular |
Delhi | Up to 33 kV | Department of Power notification, 4 January 2017, self-certification by the owner through electrical safety engineers |
Both state notifications were issued under the 2010 regulations. The 2023 regulations keep the same mechanism, but we could not confirm whether either state has re-notified, so ask the state inspectorate for the current notification before planning a project around these figures. Other states' numbers are in circulation; we have not checked them, so the table stops at three.
What the inspector's form asks to see
For installations above 650 V the report is Form III of Schedule II to the regulations. It opens with the installation's particulars (transformers, generators, motors, switchgear, connected load), then asks yes-or-no questions about its general condition, then asks for equipment-wise test results with the actual numbers filled in.
The general-condition questions include:
Whether an ESO has been designated and the record of designated persons is up to date.
Whether transformer oil samples are tested periodically and the results recorded, with the dielectric strength stated.
Whether earth resistance is measured once a year and the record attached.
Whether lightning arresters are fitted near the transformers.
The protection schemes and their settings.
Whether residual life assessment and life-extension programmes are under way for equipment more than 15 years old.
Fencing, oil soak pits and fire-fighting arrangements in the substation.
The test table is the part that needs numbers on file:
Equipment | Results the form asks for |
Isolator | Mechanical, local and remote operation, contact resistance, interlocking with the earth switch and the breaker, insulation resistance open and closed |
Circuit breaker | Insulation resistance open and closed, contact resistance including dynamic contact resistance, mechanical operation and timing, interlocks, alarm and trip for oil and winding temperature, Buchholz and pressure relief, earth fault, overcurrent and undervoltage relays |
Transformer | Insulation resistance (HT to LT, HT to earth, LT to earth), breakdown voltage of top and bottom oil samples, vector group, polarity, magnetic balance, tan delta, oil levels, temperature indicator settings, Buchholz and pressure relief operation, tap changer operation, body and neutral earth resistance, SFRA, DFRA, partial discharge |
Current and potential transformers | Ratio, polarity, oil breakdown voltage, insulation resistance, tan delta and capacitance |
Cables | Insulation resistance phase to phase and phase to earth |
Earthing | Resistance of each electrode and of the earth mat |
The form says these details are to be given "if applicable". A plant that has the commissioning values and last year's shutdown values on file can fill the table from its own records. A plant that does not has to produce them on the inspector's timetable.
When approval is needed again
Regulation 45 asks for inspection (above the notified voltage) or self-certification (at or below it) before supply begins, before supply restarts after a shutdown of six months or more, and before any addition or alteration is connected. A new transformer, an extra HT panel or a higher-rated replacement transformer is an addition or alteration in the ordinary sense of those words, so plan for approval before you energise. A bigger sanctioned load with no change to the equipment is a different case: under regulation 33(1) the supplier tests the installation, or accepts results signed by a licensed electrical contractor, before additional supply starts.
Before applying, the owner of an installation above the notified voltage tests every circuit (other than an overhead line) to show it withstands the testing voltage, records the results and submits them (regulation 45(5)). Regulation 48 also requires site tests on new apparatus above 650 V before commissioning, lets the Inspector ask for the manufacturer's type, acceptance and routine test certificates, and says test, tripping, maintenance and repair records must be kept so they can be compared with past records.
What happens when a defect is ignored
When the Electrical Inspector reports defects and the owner does not fix them in the time given, the installation can be disconnected after a notice of not less than 48 hours (regulation 32(7)). An appeal under section 162(2) of the Electricity Act, with a stay from the appellate authority, stops the disconnection.
The Act's penalty for not following an order or direction, section 146, changed on 1 June 2026 under the Jan Vishwas (Amendment of Provisions) Act, 2026. SCC Online's note on the amendment gives a fine of INR 10,000 to INR 10 lakh for each offence, plus INR 1,000 to INR 50,000 a day if non-compliance continues after conviction. Imprisonment is not mentioned. Which provision applies to which lapse is a legal question, so take it to your counsel.
Staying ready between inspections
The inspector's form is answered from a plant's own files, so the plant that tests on a rhythm and writes the numbers down has the easier inspection. A workable rhythm follows the form: a yearly set run through the ESO, a second set at each planned shutdown, and a fresh baseline after every change.
Every year, through the ESO: insulation resistance on transformers and cables, earth resistance of electrodes and the mat, a transformer oil sample with the breakdown voltage recorded, protection and alarm checks, and a refresh of the designated-persons record.
At each planned shutdown: breaker contact resistance and timing, relay injection tests, current and potential transformer checks, and an infrared scan of panels and joints.
After any addition or alteration: the approval or self-certification before energising, and a new baseline set of readings.
Grade Electricals sells this work, so weigh this paragraph accordingly. Its maintenance and testing page lists transformer testing and oil analysis, HV and LV cable tests, breaker contact resistance and timing, current and potential transformer tests, earthing measurements, protection relay injection tests and thermographic imaging for HV equipment up to 33 kV. Its liaisoning page names the Electrical Inspector's office, MSEDCL, BEST, Tata Power and Adani Electricity among the authorities it deals with. For a project, the turnkey projects page covers LV and HV electrification up to 33 kV, and the CEIG approval guide for Maharashtra covers the state's approval route. The equipment behind the form is covered in the 33/11 kV substation guide and the guide to yearly transformer tests. To discuss a plant, use the contact page.
Questions factories ask
What is rule 32 electrical inspection?
It is regulation 32 of the 2023 regulations, periodic inspection and testing. Installations above the notified voltage are inspected by the Electrical Inspector, and those at or below it are self-certified by the owner. In the 2010 regulations the same duty sat in regulation 30.
Is rule 43 the same as regulation 45 now?
The approval duty before supply starts was regulation 43 in 2010 and is regulation 45 in 2023. Regulation 45 also covers restarts after six months or more and additions and alterations.
What is a five-year periodic electrical inspection?
Five years is the ceiling in regulation 32(2), not a standard interval. The state government directs the actual period and can set it shorter.
Is an Electrical Safety Officer mandatory for a factory?
Yes, for a factory registered under the Factories Act, 1948 with a connected load above 250 kW (regulation 5(3)).